Indore-Ujjain six lane road construction company will be selected by July.

750 crores will be spent on 44 km long road

Madhya Pradesh Road Development Corporation will select the company to do the work of Indore-Ujjain six lane project by July.
The tender process for this has been completed and the tenders of the companies have come.
This 44 kilometer long road is estimated to cost around Rs 750 crore.

In view of Simhastha, the state government intends to complete the said project as soon as possible, so that the visiting devotees do not get disturbed.
At present the Indore-Ujjain road is four lanes wide, but during Sinhastha there is frequent long traffic jams, due to which people get troubled.
Chief Minister Dr. Mohan Yadav himself seeks answers from officers from time to time regarding this project.
This is the reason why MPRDC has kept this project on top priority.

indore-ujjain six lane road

Aurobindo to Harifatak will be built in two years

According to the source, MPRDC General Manager Rakesh Jain said that Indore-Ujjain six lane road is to be built from Aurobindo Hospital to Harifatak in Ujjain.
This state highway, which is being built 45 meters wide, does not require much land, hence the work can be done quickly.
MPRDC will take the contract and give the agency a time limit of two years to complete the work.

Conclusion :-

Along with the preparations for this six-lane highway, the rates of properties around Indore-Ujjain road are also increasing drastically. Jain Real Estate Advisory has the best location you can invest in. With the preparation of new infrastructure, many investors are interested to invest at Super Corridor and Ujjain Road. Along with this, metro train can be started on Indore Ujjain Highway on the occasion of Sinhastha, which will reduce the traffic on the roads and the public will get an opportunity to travel safely and fast.